As of today, March 18, 2024 I have been informed by the Project Manager of the progress of the Charter/Spectrum project for the Town of Hustisford,  It is as follows:

Currently all construction has been finished in the Town of Hustisford. 

Restoration crews should be coming through in the next 4-6 weeks, weather permitting.  

South of Hwy 60 should be active and ready for hook-up approximately by the end of April, beginning of May.